Selecting an access control power supply starts with three questions: what voltage each lock and controller permits, how much current is needed during actuation, and which functions must remain available when mains fails. Then check the supply, battery, control contacts, enclosure and wiring as one system.

This guide follows load sizing, output selection, backup, wiring and acceptance checks, using the original Sanyi Power MJ-60A/MJ-60B datasheets to distinguish real configurations. Numerical examples below illustrate calculations; they are not measured lock specifications, customer cases or runtime promises.

1. Separate lock-control supplies, EPS backup and power boxes

Product directionCheck firstDo not assume from its name
Access control supplyLock control, output channels and battery managementNO/NC contacts, delay or permissible load per channel
EPS DC backup supplyFloat charging, mains/battery selection and circuit countDedicated lock contacts or equivalence to high-power building AC EPS
Access control power boxModule, terminals, installation and battery spaceAn included battery, electrical compatibility or guaranteed runtime

For normally open/closed lock control, verify that the exact model specifies the function. For multiple DC circuits requiring backup, compare the 43/53/63 EPS DC backup range. Review access control power boxes for cabinet requirements, while checking battery compatibility independently of physical space.

2. Build a load schedule before choosing amperes

Required informationWhy it matters
Exact device and allowable input rangeNominal 12V or 24V is not the full permitted range
Hold and actuation currentSteady and transient loads can differ
Simultaneous actions and durationEstablishes the worst load step
Functions required during an outageDefines the battery discharge load
One-way cable distance and conductor sizeDetermines voltage at the equipment, not just the PSU
Circuit separation and interlock requirementsDefines control contacts and fault interactions

Start with Steady load current = sum of actual steady currents. As a calculation example, two locks at 0.5A each, a 0.3A controller and readers totaling 0.2A produce a 1.5A steady load. Any additional actuation peaks must be checked for amplitude, simultaneous operation and duration. The 1.5A result is not an all-conditions limit.

After mains returns, the supply may power the load while charging the battery. Check that combined operating condition when sizing the PSU. During an outage, calculate battery capacity from the discharge load; do not add mains-restoration charging current again as battery discharge current.

3. A 12V label does not establish compatibility with every output

PSU output, permitted equipment input and battery-bus voltage are different quantities. Backup systems may use a charging voltage above the battery nominal voltage. The connected equipment must tolerate the actual range.

For example, MJ-60B lists a 13.8V main output V1, an independent 12V output V2 and a 13.8V charging channel V3. These are not three interchangeable 12V load terminals. Check the lock, controller and reader limits before connecting nominal 12V equipment to 13.8V.

For 24V equipment, select a compatible output and backup architecture. The MJ-60A 21V or 30V columns must not be advertised as a universal 24V output; confirm the exact configuration, adjustment range and charging arrangement.

4. MJ-60A vs MJ-60B: compare channels and control

ItemMJ-60AMJ-60B
Voltage information13.8V, 21V and 30V columns; confirm the configurationV1: 13.8V; V2: 12V; V3: 13.8V charging
Lock controlCheck the selected A-version diagramExplicit NO/NC function
Release delayDo not import B-model functionsAdjustable 0–15s
Independent 12V channelVerify the applicable configurationV2 is 12V/1A; the datasheet describes camera use
Battery chargingCheck the applicable voltage-column dataV3 is 13.8V/1A; listed discharge protection is 10.5V
Operating boundaryCheck voltage, current and rated power togetherReview main, auxiliary and charging loads together

Sources: MJ-60A original PDF and MJ-60B original PDF. Both documents list 100–240Vac, 50/60Hz input and describe short-circuit, overload, overvoltage and battery over-discharge functions. Confirm protection mode, wiring, rated-power limits and certification scope for the supplied revision. Adding current columns does not establish a guaranteed total output rating.

5. Wiring: distinguish power terminals from control terminals

With power isolated, use the exact model diagram to identify:

  1. mains L/N and protective earth FG;
  2. load polarity and the permitted current of each channel;
  3. battery BAT polarity and the charging connection;
  4. NO/NC, COM and release-control terminals;
  5. the control relationship between lock, controller and exit devices.

Terminal order and logic can change between models. Do not wire by enclosure appearance. NO/NC contacts, a lock's unpowered state and project interlocks are also different concepts. Qualified personnel should confirm installation and testing against device instructions, system design and applicable project requirements.

6. Battery sizing: separate an assumption from a runtime promise

A first capacity estimate is:

Theoretical Ah ≈ outage load current × target hours ÷ usable-capacity factor

For an example 1.5A outage load, a 4-hour target and an assumed 0.7 usable factor, capacity is approximately 1.5 × 4 ÷ 0.7 = 8.6Ah. Four hours and 0.7 are calculation assumptions, not universal requirements or battery guarantees.

The final selection must consider chemistry, temperature, ageing, discharge rate, low-voltage cut-off, cable losses and recharge time. Establish the target from the project and required functions. Requirements applying to one type of fire-alarm equipment must not be transferred to an entire access control installation without verifying scope.

7. Check voltage drop at the worst operating point

For a simple DC circuit, start with Voltage drop = load current × loop resistance. Loop resistance includes both outgoing and return conductors.

An example 0.4Ω loop carrying 1.5A drops 0.6V. A correct PSU-terminal reading does not prove that the lock receives sufficient voltage. Check the battery-low bus, actuation peaks, connector resistance and cable temperature too.

Use the voltage-drop calculator for an initial estimate and measure at the real load. Before increasing system voltage, confirm that every device and control interface accepts it. Arbitrary voltage adjustment does not repair an undersized cable.

8. Acceptance checks must cover mains, outage and recovery

Test stageObserveRecord
Normal mains and lock actionsChannel/device voltage, actuation current and controller resetsLoad schedule and measured waveforms or readings
Mains removalBattery operation, required functions and continuityLoad, battery condition, duration and environment
Mains restorationLoad plus battery charging and any repeated transferCharging current, temperature and recovery
Control and delayNO/NC logic, delay and project interlocksExact terminal diagram and settings
Protection and recoveryDatasheet-defined response and resetQualified testing under an approved procedure

Hold-up time is not mains-to-battery transfer time and does not guarantee that a particular controller will avoid restarting. Validate the exact supply/battery/load combination. Check certification and EMC scope for the model, market and final system rather than assuming that a displayed mark covers every configuration.

FAQ

Does every access control power supply require the same certification?

No single label establishes suitability for every project. Check the location, final system, specification and authority requirements, then verify valid documents covering the exact configuration. A test-standard reference in a datasheet is not proof that every version has the corresponding certification.

Must an access control battery provide four hours of backup?

Do not treat four hours as a universal requirement. Establish the functions, project requirements and interlocks first, then size the battery and recharge arrangement. The duration in this guide is an example only.

Can door locks and cameras use the same supply?

Check channels and system design. MJ-60B explicitly describes an independent 12V output for camera use, but its 1A channel limit, total power, transients and fault interactions still need verification. Neither compulsory sharing nor a blanket prohibition is appropriate for every installation.

How should I choose between an access control supply and EPS backup?

For lock control, check NO/NC, release delay and interfaces. For multi-circuit DC backup, compare the 43 Series EPS selection data and complete EPS range. A battery connection alone does not make the products interchangeable.

What helps obtain the right configuration and quotation?

Send equipment models, allowable voltage, steady/actuation current, cable distances, battery/runtime target, cabinet space and quantity. Review original documents on the MJ access control supply page, then contact Sanyi Power. Pricing, delivery and after-sales arrangements follow the specific product and mutually confirmed order.

Serving 30+ countries
20+ years in power R&D
Compliance documents by model

Need a power supply for your project?

Share your application, input/output requirements, quantity and target market to discuss selection and a quote. Confirm compliance documents for the selected model and version.

Related Products

MJ Series
MJ Series
Access Control Dedicated Power Supply
View Details
Access Control Box
Access Control Box
Access Control Power Box 60W-75W
View Details
SY-A / FYBG Series
SY-A / FYBG Series
Surveillance Dedicated Centralized Power Distribution Box
View Details